<?php
// Gantt example to create CSIM using CreateSimple()

include ("../jpgraph.php");
include (
"../jpgraph_gantt.php");

$data = array(
  array(
0,ACTYPE_GROUP,    "Phase 1",        "2001-10-26","2001-11-23",'',
    
'#1','Go home'),
  array(
1,ACTYPE_NORMAL,   "  Label 2",      "2001-10-26","2001-11-16",'ab,cd',
    
'#2','Go home'),
  array(
2,ACTYPE_NORMAL,   "  Label 3",      "2001-11-20","2001-11-22",'ek',
    
'#3','Go home'),
  array(
3,ACTYPE_MILESTONE,"  Phase 1 Done""2001-11-23",'M2',
    
'#4','Go home') );

// The constrains between the activities
$constrains = array(array(1,2,CONSTRAIN_ENDSTART),
            array(
2,3,CONSTRAIN_STARTSTART));

$progress = array(array(1,0.4));

$graph = new GanttGraph(500);
$graph->title->Set("Example with image map");
$graph->ShowHeaders(GANTT_HYEAR GANTT_HMONTH GANTT_HDAY GANTT_HWEEK);
$graph->scale->week->SetStyle(WEEKSTYLE_FIRSTDAY);
$graph->scale->week->SetFont(FF_FONT1);

$graph->CreateSimple($data,$constrains,$progress);

// Add the specified activities
//SetupSimpleGantt($graph,$data,$constrains,$progress);

// And stroke
$graph->StrokeCSIM('ganttcsimex02.php');


?>